Wake-up call: The floods that hit Penang in 2017 exposed its lack of flood mitigation and disaster preparedness.
GEORGE TOWN: The south-west monsoon season is expected to start sometime this month, prompting fears of flooding and falling trees here.
As dark clouds hang over Penang almost every morning now to herald the coming monsoon, talk of flooding in the state assembly sitting on Tuesday led to several lawmakers and the Speaker himself wanting to have a say.
“I am aware that some government agencies belittle the efforts of assemblymen who highlight flooding and other problems.
“As legislators who face the rakyat, they are carrying out their duties and I hope that the relevant agencies will take them seriously and not make fun of them,” said Speaker Datuk Law Choo Kiang during the day’s proceedings.
Lim Siew Khim (PH-Sungai Pinang) told the assembly how she and Ong Ah Teong (PH-Batu Lanchang) suffered verbal insults when visiting flood victims in Kampung Bukit Dumbar, where homes were flooded seven times, including a few days before the recent Chinese New Year.
This led to Dr Norlela Ariffin (PH-Penanti), Ong and Teh Lai Heng (PH-Komtar) to also stand up and voice their grouses.
Outside the hall, Ong said government officers handling flood problems tend to ignore the pleas of assemblymen.
“We are all in the same WhatsApp groups. When we highlight floods, they never respond,” he said.
Teh told the assembly that government officers don’t face the residents but the assemblymen bear all the insults from flood victims in their constituencies.
Dr Norlela said when she attended the monthly district meetings and called for strict enforcement to end the source of floodings such as deforestation, her pleas were often met with silence.
While the Sungai Pinang Flood Mitigation Plan – delayed for 20 years – has begun again with renewed federal funding, many are worried that the south-west monsoon will still bring back the floods this year.
Scientists Sheeba Nettukandy Chenoli and Chai Heng Lim, in a research paper published last November in the “Journal of Atmospheric and Solar-Terrestrial Physics”, found that the onset of the mid-year monsoon will be on May 19 with a standard deviation of eight days.
State Environment Committee chairman Phee Boon Poh said this was the season when rain coinciding with extra high tides fuelled by the super full moon could lead to severe flooding.
“Between May and June, strong winds stir up huge tidal waves that are not safe for small boats,” he said.
A freak storm on Sunday caused several trees to fall on Penang island, one of them in Tanjung Bungah falling on a passing car.
To keep falling trees in check, State Works Committee chairman Zairil Khir Johari said a special committee was ironing out a method to pass the care of public trees from the Public Works Department (JKR) to Penang Island City Council (MBPP).
“JKR specialises in building and caring for roads and bridges but MBPP has a full landscaping team that includes arborists.
“This team has the know-how to care for public trees and recognise diseased trees that must be felled before they become a hazard.
“We are finalising a method for MBPP’s landscapers to have island-wide jurisdiction of roadside trees and be granted access to federal grants for their maintenance,” he said.
Wake-up call: The floods that hit Penang in 2017 exposed its lack of flood mitigation and disaster preparedness.
GEORGE TOWN: The south-west monsoon season is expected to start sometime this month, prompting fears of flooding and falling trees here.
As dark clouds hang over Penang almost every morning now to herald the coming monsoon, talk of flooding in the state assembly sitting on Tuesday led to several lawmakers and the Speaker himself wanting to have a say.
“I am aware that some government agencies belittle the efforts of assemblymen who highlight flooding and other problems.
“As legislators who face the rakyat, they are carrying out their duties and I hope that the relevant agencies will take them seriously and not make fun of them,” said Speaker Datuk Law Choo Kiang during the day’s proceedings.
Lim Siew Khim (PH-Sungai Pinang) told the assembly how she and Ong Ah Teong (PH-Batu Lanchang) suffered verbal insults when visiting flood victims in Kampung Bukit Dumbar, where homes were flooded seven times, including a few days before the recent Chinese New Year.
This led to Dr Norlela Ariffin (PH-Penanti), Ong and Teh Lai Heng (PH-Komtar) to also stand up and voice their grouses.
Outside the hall, Ong said government officers handling flood problems tend to ignore the pleas of assemblymen.
“We are all in the same WhatsApp groups. When we highlight floods, they never respond,” he said.
Teh told the assembly that government officers don’t face the residents but the assemblymen bear all the insults from flood victims in their constituencies.
Dr Norlela said when she attended the monthly district meetings and called for strict enforcement to end the source of floodings such as deforestation, her pleas were often met with silence.
While the Sungai Pinang Flood Mitigation Plan – delayed for 20 years – has begun again with renewed federal funding, many are worried that the south-west monsoon will still bring back the floods this year.
Scientists Sheeba Nettukandy Chenoli and Chai Heng Lim, in a research paper published last November in the “Journal of Atmospheric and Solar-Terrestrial Physics”, found that the onset of the mid-year monsoon will be on May 19 with a standard deviation of eight days.
State Environment Committee chairman Phee Boon Poh said this was the season when rain coinciding with extra high tides fuelled by the super full moon could lead to severe flooding.
“Between May and June, strong winds stir up huge tidal waves that are not safe for small boats,” he said.
A freak storm on Sunday caused several trees to fall on Penang island, one of them in Tanjung Bungah falling on a passing car.
To keep falling trees in check, State Works Committee chairman Zairil Khir Johari said a special committee was ironing out a method to pass the care of public trees from the Public Works Department (JKR) to Penang Island City Council (MBPP).
“JKR specialises in building and caring for roads and bridges but MBPP has a full landscaping team that includes arborists.
“This team has the know-how to care for public trees and recognise diseased trees that must be felled before they become a hazard.
“We are finalising a method for MBPP’s landscapers to have island-wide jurisdiction of roadside trees and be granted access to federal grants for their maintenance,” he said.
Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the
committee chairman, said the MBPP as the owner of the project had failed
in its overall responsibility to supervise the project despite having
appointed Jurutera Perunding GEA as representative of the superintendent
officer. NSTP/MIKAIL ONG
MBPP among four named as responsible in fatal Penang landslide
GEORGE TOWN: Four parties have been identified as being responsible for the fatal landslide at the construction site of the paired road at Jalan Bukit Kukus last October incident, including the Penang Island City Council (MBPP).
A special investigation committee set up by the Penang government following the fatal landslide at the construction site also named the other three parties, namely the contractor Yuta Maju Sdn Bhd, the consultant, Jurutera Perunding GEA (M) Sdn Bhd and the independent checking engineer G&P Professional Sdn Bhd.
Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer.
“By appointing Jurutera Perunding GEA, it does not mean that the council is free from responsibilities to ensure the success of the project from all aspects.
"As such, any actions to be taken against the council will depend on the outcome of investigations by the police, the Department of Occupational Safety and Heath (DOSH) and the Construction Industry Development Board (CIDB) into the incident," he said when making public findings of the investigation committee.
Ahmad Zakiyuddin said as for Yuta Maju, it had failed to ensure satisfactory mitigation works at the project site, and that the temporary slope constructed at the project site was not endorsed or designed by accredited consultants, which was a violation of the Board of Engineers Malaysia (BEM) guidelines.
“It also failed to ensure site safety by removing the empty containers at the project site, where nine bodies were recovered," he added.
As for Jurutera Perunding GEA, Ahmad Zakiyuddin said the party had failed to ensure that the contractor abide by the guidelines set out by the BEM, while G&P Professional had failed to abide by the job scope given by the council.
“Following our findings, we have recommended that the contractor, consultant and independent checking engineer be blacklisted from any tender consideration for projects in the future.
“That said, they will still have to continue their works for the paired road project, until the project completion, slated for May next year,” he added.
The landslide at the Bukit Kukus paired roads project site on Oct 19 last year killed nine site workers and left four others injured.
The search and rescue (SAR) operation was called off after five days. The project's stop-work orders, separately issued by DOSH, CIDB and the council, were lifted up recently.
Ahmad Zakiyuddin said the special investigation committee also identified 10 main factors which had contributed the to fatal landslide, particularly not fully adopting best practices in construction work.
Other factors included:
* heavy rain on the morning of the incident at 55mm
* the contractor was unable to enter the project site to carry out mitigation works as stop-work order was issued by DOSH two days prior to the incident following a worksite accident
* unsafe construction processes
* failure to recognise the significance of an earlier incident (falling beams at another part of the project site two days prior to the landslide);
* lack of supervision
* failure to identify risk due to the change of process
* lack of comprehensive inspection and testing
* failure in risk communication
* poor management of sub-contractors.
Asked on why the services of the contractor, consultant and independent checking engineer were not immediately terminated following the incident, Ahmad Zakiyuddin said from what he understood, the stop-work orders issued on the three were only for one part of the project and not the entire project.
"Also, there was no record of safety issues prior to the landslide," he said.
He called on efforts to protect the remaining part of the project as a resu
lt of a negative perception.
"Any delay will put the project at greater risks."
To another question if the special investigation committee's findings would be made public, he there had been no plans to do so as the report served as a guideline for the state. - By Audrey Dermawan, NST >
‘MBPP hired resident engineer for Bukit Kukus project’
GEORGE TOWN: The Penang Island City Council (MBPP) appointed a resident engineer and an independent checking engineer even before the start of the Bukit Kukus paired road project, says Chief Minister Chow Kon Yeow.
“If you see the action taken by MBPP, they understand their technical insufficiency in terms of a geotechnical engineer. That’s why in the contract, they required the main contractor to appoint a resident engineer, who was paid by MBPP to monitor the project on MBPP’s behalf.
“The independent checking engineers were also paid by MBPP. So, it was a measure taken by MBPP even before the start of the project, knowing that this is a big project.
“They did not have the capacity to monitor the project as they have only two or three engineers who have to be looking at other matters besides this project.
“So, they took action to appoint a resident engineer as well as independent checking enginners to act on behalf of MBPP,” he told reporters at the Penang Development Corporation Chinese New Year celebration at the PDC office in Bayan Lepas yesterday.
Chow also said the state would wait for the Department of Occupational Safety and Health (DOSH) report first.
“We will leave it to DOSH’s findings. Let DOSH come out with the report and we will take the necessary action after that,” he said.
Asked if MBPP had to bear necessary compensation for families of the victims of the landslide last October, Chow said MBPP had not received any claim so far.
Chow was asked to respond to the Consumers Association of Penang’s (CAP) call for stern action to be taken against the wrongdoers responsible for the tragedy.
CAP president S.M. Mohamed Idris in a statement yesterday said: “While we welcome the investigation committee’s findings as to who is responsible for the tragedy, we are concerned that apart from recommending the blacklisting of the contractor, consultant and independent checking engineer from any tender consideration for future projects, it appears that no further stern action has been recommended.
“In particular, we want to know what action will be taken against MBPP,” he said.
Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who headed the investigation panel, was reported yesterday as saying that MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired road project had not adhered to construction and engineering best practices.
Meanwhile, MBPP acknowledged responsibility for the Bukit Kukus landslide tragedy as it is the council’s project.
MBPP mayor Datuk Yew Tung Seang said the council was not pushing away any responsibility or negative comments on the council and project, and that it would be taken seriously. - By Cavina Lim and Intan Amalina Mohd Ali, The Star
Penang landslide report blames contractor, MBPP and DOSH
The special investigative panel report on the Bukit Kukus landslide had not been made public, but excerpts of the findings were made available by the state.
However, it has raised more questions than answers as the state blamed the contractor, Penang Island City Council (MBPP) and the Department of Occupational Safety and Health (DOSH).
In an immediate response, DOSH Penang director Jaafar Leman denied the department was to be blamed for the landslide.
“We were not even invited to be part of the investigative panel to give our views. How could we be blamed?” he asked.
According to the statement by Deputy Chief Minister 1 Datuk Ahmad Zakiyuddin Abdul Rahman who headed the investigative panel, the stop-work order on Oct 17 prevented contractors from entering the site to do maintenance works.
As a result, the temporary toe drain overflowed and water was retained on the reclaimed land contributing to the collapse of the slopes.
“How could a stop order which was issued on Oct 17 contribute to the landslide which occurred on Oct 19?” asked Jaafar.
He said the slopes would have been risky from the beginning as the contractor did not do any mitigation works to strengthen them and it does not make sense to blame DOSH.
The stop-work order was issued on Oct 17 after 14 beams fell in a ravine.
Earlier, during a press conference, Ahmad Zakiyuddin said MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired roads project, had not adhered to construction and engineering best practices.
“The landslide was caused by many factors, which included a temporary construction of a platform to place machinery which was not constructed properly. The temporary platform was created to allow heavy vehicles lift beams for the paired road project.
“MBPP, as owners of the project, had failed to ensure all the hired parties carried out their job.
“MBPP had failed to hire a professional engineer for temporary works to design and supervise the site,” he said yesterday.
Ahmad Zakiyuddin said another factor was the downpour in the morning of the day of the landslide.- The Star
Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide
tragedy. The inquiry still begs a lot of questions, e.g. why was the
contract given to Yuta Maju from Terengganu? Could the accident have
been prevented if a proper EIA was done? It is not just a "bureaucratic
hurdle" but supposed to identify risks and advise mitigation. If the
authorities wish to go on with the project, it is not too late to
commissi... See more
“This
is no simple incident as nine deaths resulted from it. Very stern
action must be taken against the MBPP, and that includes strong
disciplinary action against the mayor and officers responsible.
“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.
Dubious honours: (Above) Former Penang Island City Council mayor
Patahiyah Ismail with the trophy and certificate for Best Municipal
Manager awards in 2013 while her Seberang Prai counterpart Maimunah
(pictured here with the Chief Minister Lim Guan Eng and his aide Wong
Hon Wai) received the same latter award in 2014
Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer. NSTP/MIKAIL ONG
MBPP among four named as responsible in fatal Penang landslide
GEORGE TOWN: Four parties have been identified as being responsible for the fatal landslide at the construction site of the paired road at Jalan Bukit Kukus last October incident, including the Penang Island City Council (MBPP).
A special investigation committee set up by the Penang government following the fatal landslide at the construction site also named the other three parties, namely the contractor Yuta Maju Sdn Bhd, the consultant, Jurutera Perunding GEA (M) Sdn Bhd and the independent checking engineer G&P Professional Sdn Bhd.
Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer.
“By appointing Jurutera Perunding GEA, it does not mean that the council is free from responsibilities to ensure the success of the project from all aspects.
"As such, any actions to be taken against the council will depend on the outcome of investigations by the police, the Department of Occupational Safety and Heath (DOSH) and the Construction Industry Development Board (CIDB) into the incident," he said when making public findings of the investigation committee.
Ahmad Zakiyuddin said as for Yuta Maju, it had failed to ensure satisfactory mitigation works at the project site, and that the temporary slope constructed at the project site was not endorsed or designed by accredited consultants, which was a violation of the Board of Engineers Malaysia (BEM) guidelines.
“It also failed to ensure site safety by removing the empty containers at the project site, where nine bodies were recovered," he added.
As for Jurutera Perunding GEA, Ahmad Zakiyuddin said the party had failed to ensure that the contractor abide by the guidelines set out by the BEM, while G&P Professional had failed to abide by the job scope given by the council.
“Following our findings, we have recommended that the contractor, consultant and independent checking engineer be blacklisted from any tender consideration for projects in the future.
“That said, they will still have to continue their works for the paired road project, until the project completion, slated for May next year,” he added.
The landslide at the Bukit Kukus paired roads project site on Oct 19 last year killed nine site workers and left four others injured.
The search and rescue (SAR) operation was called off after five days. The project's stop-work orders, separately issued by DOSH, CIDB and the council, were lifted up recently.
Ahmad Zakiyuddin said the special investigation committee also identified 10 main factors which had contributed the to fatal landslide, particularly not fully adopting best practices in construction work.
Other factors included:
* heavy rain on the morning of the incident at 55mm
* the contractor was unable to enter the project site to carry out mitigation works as stop-work order was issued by DOSH two days prior to the incident following a worksite accident
* unsafe construction processes
* failure to recognise the significance of an earlier incident (falling beams at another part of the project site two days prior to the landslide);
* lack of supervision
* failure to identify risk due to the change of process
* lack of comprehensive inspection and testing
* failure in risk communication
* poor management of sub-contractors.
Asked on why the services of the contractor, consultant and independent checking engineer were not immediately terminated following the incident, Ahmad Zakiyuddin said from what he understood, the stop-work orders issued on the three were only for one part of the project and not the entire project.
"Also, there was no record of safety issues prior to the landslide," he said.
He called on efforts to protect the remaining part of the project as a resu
lt of a negative perception.
"Any delay will put the project at greater risks."
To another question if the special investigation committee's findings would be made public, he there had been no plans to do so as the report served as a guideline for the state. - By Audrey Dermawan, NST >
‘MBPP hired resident engineer for Bukit Kukus project’
GEORGE TOWN: The Penang Island City Council (MBPP) appointed a resident engineer and an independent checking engineer even before the start of the Bukit Kukus paired road project, says Chief Minister Chow Kon Yeow.
“If you see the action taken by MBPP, they understand their technical insufficiency in terms of a geotechnical engineer. That’s why in the contract, they required the main contractor to appoint a resident engineer, who was paid by MBPP to monitor the project on MBPP’s behalf.
“The independent checking engineers were also paid by MBPP. So, it was a measure taken by MBPP even before the start of the project, knowing that this is a big project.
“They did not have the capacity to monitor the project as they have only two or three engineers who have to be looking at other matters besides this project.
“So, they took action to appoint a resident engineer as well as independent checking enginners to act on behalf of MBPP,” he told reporters at the Penang Development Corporation Chinese New Year celebration at the PDC office in Bayan Lepas yesterday.
Chow also said the state would wait for the Department of Occupational Safety and Health (DOSH) report first.
“We will leave it to DOSH’s findings. Let DOSH come out with the report and we will take the necessary action after that,” he said.
Asked if MBPP had to bear necessary compensation for families of the victims of the landslide last October, Chow said MBPP had not received any claim so far.
Chow was asked to respond to the Consumers Association of Penang’s (CAP) call for stern action to be taken against the wrongdoers responsible for the tragedy.
CAP president S.M. Mohamed Idris in a statement yesterday said: “While we welcome the investigation committee’s findings as to who is responsible for the tragedy, we are concerned that apart from recommending the blacklisting of the contractor, consultant and independent checking engineer from any tender consideration for future projects, it appears that no further stern action has been recommended.
“In particular, we want to know what action will be taken against MBPP,” he said.
Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who headed the investigation panel, was reported yesterday as saying that MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired road project had not adhered to construction and engineering best practices.
Meanwhile, MBPP acknowledged responsibility for the Bukit Kukus landslide tragedy as it is the council’s project.
MBPP mayor Datuk Yew Tung Seang said the council was not pushing away any responsibility or negative comments on the council and project, and that it would be taken seriously. - By Cavina Lim and Intan Amalina Mohd Ali, The Star
Penang landslide report blames contractor, MBPP and DOSH
The special investigative panel report on the Bukit Kukus landslide had not been made public, but excerpts of the findings were made available by the state.
However, it has raised more questions than answers as the state blamed the contractor, Penang Island City Council (MBPP) and the Department of Occupational Safety and Health (DOSH).
In an immediate response, DOSH Penang director Jaafar Leman denied the department was to be blamed for the landslide.
“We were not even invited to be part of the investigative panel to give our views. How could we be blamed?” he asked.
According to the statement by Deputy Chief Minister 1 Datuk Ahmad Zakiyuddin Abdul Rahman who headed the investigative panel, the stop-work order on Oct 17 prevented contractors from entering the site to do maintenance works.
As a result, the temporary toe drain overflowed and water was retained on the reclaimed land contributing to the collapse of the slopes.
“How could a stop order which was issued on Oct 17 contribute to the landslide which occurred on Oct 19?” asked Jaafar.
He said the slopes would have been risky from the beginning as the contractor did not do any mitigation works to strengthen them and it does not make sense to blame DOSH.
The stop-work order was issued on Oct 17 after 14 beams fell in a ravine.
Earlier, during a press conference, Ahmad Zakiyuddin said MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired roads project, had not adhered to construction and engineering best practices.
“The landslide was caused by many factors, which included a temporary construction of a platform to place machinery which was not constructed properly. The temporary platform was created to allow heavy vehicles lift beams for the paired road project.
“MBPP, as owners of the project, had failed to ensure all the hired parties carried out their job.
“MBPP had failed to hire a professional engineer for temporary works to design and supervise the site,” he said yesterday.
Ahmad Zakiyuddin said another factor was the downpour in the morning of the day of the landslide.- The Star
Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide tragedy. The inquiry still begs a lot of questions, e.g. why was the contract given to Yuta Maju from Terengganu? Could the accident have been prevented if a proper EIA was done? It is not just a "bureaucratic hurdle" but supposed to identify risks and advise mitigation. If the authorities wish to go on with the project, it is not too late to commissi... See more
“This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.
“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.
Dubious honours: (Above) Former Penang Island City Council mayor Patahiyah Ismail with the trophy and certificate for Best Municipal Manager awards in 2013 while her Seberang Prai counterpart Maimunah (pictured here with the Chief Minister Lim Guan Eng and his aide Wong Hon Wai) received the same latter award in 2014