Monday, October 15, 2018

Bukit Kukus paired road hits snag before mishap, stop work order to contractor on collapsed beams

Precarious situation: The collapsed beams along Jalan Tun Sardon which fell and broke after being knocked down.

https://www.thestar.com.my/news/nation/2018/10/14/stop-work-road-contractor-told-dosh-to-look-at-work-sites-procedures-after-mishap/?jwsource=twi

Stop work, road contractor told


BALIK PULAU: The contractor of the 600m elevated road project linking Jalan Bukit Kukus to Jalan Tun Sardon here has been issued with a stop-work order.

The order came following a mishap on the site where 14 concrete beams measuring 25m each fell onto a slope in Jalan Tun Sardon on Thursday.

Eleven beams broke apart in the 8.30pm incident. However, no injuries were reported.

It is learnt that a crane operator accidentally knocked down one of the beams laid on the ground, causing others to fall onto the slope like dominoes.

Penang Department of Occupa­tional Safety and Health (DOSH) director Mohd Rosdee Yaacob said the contractor had been instructed to be present at the DOSH office tomorrow for a meeting.

“We are reviewing the standard operating procedures at the work site.

“For now, the contractor is not allowed to load and unload other concrete beams,” he said yesterday

Mohd Rosdee said his officers were only sent to the site on Friday as they were not immediately informed of the incident.

State Works Committee chairman Zairil Khir Johari said the contractor had been told to prepare a full report for DOSH.

He said the Penang Island City Council (MBPP) would also initiate an internal inquiry tomorrow.

The construction of the elevated road, together with the upgrading of a 1.1km stretch along Lebuhraya Thean Teik and a 1.5km stretch along Lebuh Bukit Jambul, is a MBPP project costing RM275.6mil and is scheduled for completion early next year.

The three segments are part of the project for the construction of the RM545mil alternative road – Jalan Bukit Kukus – to help ease traffic snarls along Jalan Paya Terubong, which is an arterial road linking Bayan Baru, Balik Pulau and Air Itam.

The construction works involve linking Lebuhraya Thean Teik in Bandar Baru Air Itam and Lebuh Bukit Jambul in Penang via Jalan Bukit Kukus, building an elevated U-turn along Lebuh Bukit Jambul for those who want to make a turn and go back to Relau. - The Star

Paired road already hits snag

Slow path ahead: The elevated road near Jalan Paya Terubong in Penang will not be ready for another two years.
GEORGE TOWN: Work on the RM545mil Jalan Bukit Kukus paired road project has hit a snag even before the construction mishap in Jalan Tun Sardon.

The completion date on the project, an alternative road linking Lebuhraya Thean Teik in Bandar Baru Air Itam to Lebuh Bukit Jambul, will be delayed by a year till mid-2020 due to unforeseen obstacles during construction.

State Works, Utilities and Flood Mitigation committee chairman Zairil Khir Johari, in describing the project as “very complicated”, said it was constructed by three parties as a cost-saving measure.

“The Penang Island City Council (MBPP) will construct 2.8km of the stretch, while PLB Land Sdn Bhd and Geo Valley Sdn Bhd will construct the remaining 1.4km and 0.7km respectively,” he said.

Zairil said while the three parties involved in the works faced various issues resulting in the delay.

“For example, the MBPP which is working on the 2.8km stretch costing RM275.6mil, faced a delay due to land acquisition issues, realignment and relocation of cables.

“The project is 69% done and to be completed by early 2020.

“PLB Land faced issues with big rocks and boulders. The RM150mil section has progressed 36% and scheduled for mid-2020,” he said.

Zairil said that Geo Valley faced legal issues as the residents affected by their section of the project took up matters with the Appeals Board and the case was pending.

The RM120mil stretch by Geo Valley is now 18% completed.

“Once PLB and Geo Valley complete their portions, we will connect them accordingly,” he said.

It was earlier reported that the contractor of the 600m elevated road project linking Jalan Bukit Kukus to Jalan Tun Sardon was issued with a stop-work order.

The order came after a mishap on the site where 14 concrete beams measuring 25m fell onto a slope in Jalan Tun Sardon on Thursday. No injuries were reported.

It is learnt that a crane operator accidentally knocked down one of the beams laid on the ground, causing others to fall onto the slope.

Paya Terubong assemblyman Yeoh Soon Hin hopes that there will be no further delays.

“About 60,000 vehicles use Jalan Paya Terubong daily to get to Bayan Lepas, and traffic congestion is bad during peak hours.

“I hope the project will be completed safely according to specifications and on schedule for the people to use,” he said.

Once the alternative route is completed, traffic is expected to see a reduction of at least 30%.

The new link will comprise a dual carriageway with a bicycle lane, walkway and LED street lights.

A small waterfall on the hill will also be retained and construction would go around the waterfall.

Last month, MBPP mayor Datuk Yew Tung Seang said the construction on the paired road would take up RM44.2mil of the council’s budget next year. - The Star by Lo Tern Chern


Related:


Dosh: Stop-work order on elevated road project stays 

 

Public talks heading nowhere - Metro News



Penang Forum wants eco-review of PIL 1



The Tips and Procedures for Issuing a Stop Work Order


2 Things You Should Never Say To A Contractor - Residential ...





Related posts:



ART - Can be completed within 1 year for Penang lang, wait no more ! 年内就可以通车。槟城人,要不要?! The ART (Autonomous Rail-Rapid Transit) was nomi...



Penang bald Hillslopes a "time bomb"

 

Penang Paya Terubong Residents living under shadow of fear!

 

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development 

 

IJM hill clearing & Trehaus construction damaged nearby houses since 2014 must be mitigated quickly

 

Bukit Kukus paired road hits snag before mishap, stop work order to contractor on collapsed beams

Precarious situation: The collapsed beams along Jalan Tun Sardon which fell and broke after being knocked down.

https://www.thestar.com.my/news/nation/2018/10/14/stop-work-road-contractor-told-dosh-to-look-at-work-sites-procedures-after-mishap/?jwsource=twi

Stop work, road contractor told


BALIK PULAU: The contractor of the 600m elevated road project linking Jalan Bukit Kukus to Jalan Tun Sardon here has been issued with a stop-work order.

The order came following a mishap on the site where 14 concrete beams measuring 25m each fell onto a slope in Jalan Tun Sardon on Thursday.

Eleven beams broke apart in the 8.30pm incident. However, no injuries were reported.

It is learnt that a crane operator accidentally knocked down one of the beams laid on the ground, causing others to fall onto the slope like dominoes.

Penang Department of Occupa­tional Safety and Health (DOSH) director Mohd Rosdee Yaacob said the contractor had been instructed to be present at the DOSH office tomorrow for a meeting.

“We are reviewing the standard operating procedures at the work site.

“For now, the contractor is not allowed to load and unload other concrete beams,” he said yesterday

Mohd Rosdee said his officers were only sent to the site on Friday as they were not immediately informed of the incident.

State Works Committee chairman Zairil Khir Johari said the contractor had been told to prepare a full report for DOSH.

He said the Penang Island City Council (MBPP) would also initiate an internal inquiry tomorrow.

The construction of the elevated road, together with the upgrading of a 1.1km stretch along Lebuhraya Thean Teik and a 1.5km stretch along Lebuh Bukit Jambul, is a MBPP project costing RM275.6mil and is scheduled for completion early next year.

The three segments are part of the project for the construction of the RM545mil alternative road – Jalan Bukit Kukus – to help ease traffic snarls along Jalan Paya Terubong, which is an arterial road linking Bayan Baru, Balik Pulau and Air Itam.

The construction works involve linking Lebuhraya Thean Teik in Bandar Baru Air Itam and Lebuh Bukit Jambul in Penang via Jalan Bukit Kukus, building an elevated U-turn along Lebuh Bukit Jambul for those who want to make a turn and go back to Relau. - The Star

Paired road already hits snag

Slow path ahead: The elevated road near Jalan Paya Terubong in Penang will not be ready for another two years.
GEORGE TOWN: Work on the RM545mil Jalan Bukit Kukus paired road project has hit a snag even before the construction mishap in Jalan Tun Sardon.

The completion date on the project, an alternative road linking Lebuhraya Thean Teik in Bandar Baru Air Itam to Lebuh Bukit Jambul, will be delayed by a year till mid-2020 due to unforeseen obstacles during construction.

State Works, Utilities and Flood Mitigation committee chairman Zairil Khir Johari, in describing the project as “very complicated”, said it was constructed by three parties as a cost-saving measure.

“The Penang Island City Council (MBPP) will construct 2.8km of the stretch, while PLB Land Sdn Bhd and Geo Valley Sdn Bhd will construct the remaining 1.4km and 0.7km respectively,” he said.

Zairil said while the three parties involved in the works faced various issues resulting in the delay.

“For example, the MBPP which is working on the 2.8km stretch costing RM275.6mil, faced a delay due to land acquisition issues, realignment and relocation of cables.

“The project is 69% done and to be completed by early 2020.

“PLB Land faced issues with big rocks and boulders. The RM150mil section has progressed 36% and scheduled for mid-2020,” he said.

Zairil said that Geo Valley faced legal issues as the residents affected by their section of the project took up matters with the Appeals Board and the case was pending.

The RM120mil stretch by Geo Valley is now 18% completed.

“Once PLB and Geo Valley complete their portions, we will connect them accordingly,” he said.

It was earlier reported that the contractor of the 600m elevated road project linking Jalan Bukit Kukus to Jalan Tun Sardon was issued with a stop-work order.

The order came after a mishap on the site where 14 concrete beams measuring 25m fell onto a slope in Jalan Tun Sardon on Thursday. No injuries were reported.

It is learnt that a crane operator accidentally knocked down one of the beams laid on the ground, causing others to fall onto the slope.

Paya Terubong assemblyman Yeoh Soon Hin hopes that there will be no further delays.

“About 60,000 vehicles use Jalan Paya Terubong daily to get to Bayan Lepas, and traffic congestion is bad during peak hours.

“I hope the project will be completed safely according to specifications and on schedule for the people to use,” he said.

Once the alternative route is completed, traffic is expected to see a reduction of at least 30%.

The new link will comprise a dual carriageway with a bicycle lane, walkway and LED street lights.

A small waterfall on the hill will also be retained and construction would go around the waterfall.

Last month, MBPP mayor Datuk Yew Tung Seang said the construction on the paired road would take up RM44.2mil of the council’s budget next year. - The Star by Lo Tern Chern


Related:



Dosh: Stop-work order on elevated road project stays 

 


Public talks heading nowhere - Metro News


Penang Forum wants eco-review of PIL 1



The Tips and Procedures for Issuing a Stop Work Order


2 Things You Should Never Say To A Contractor - Residential ...




Related posts:



ART - Can be completed within 1 year for Penang lang, wait no more ! 年内就可以通车。槟城人,要不要?! The ART (Autonomous Rail-Rapid Transit) was nomi...


Penang bald Hillslopes a "time bomb"

 

Penang Paya Terubong Residents living under shadow of fear!

 

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development 

 

IJM hill clearing & Trehaus construction damaged nearby houses since 2014 must be mitigated quickly

 

Sunday, July 29, 2018

Has Penang Island’s growth & development become a hazard to life?



  • Malaysia’s Penang Island has undergone massive development since the 1960s, a process that continues today with plans for transit and land-reclamation megaprojects.

  • The island is increasingly facing floods and landslides, problems environmentalists link to paving land and building on steep slopes.

  • This is the second in a six-part series of articles on infrastructure projects in Peninsular Malaysia.

    GEORGE TOWN, Malaysia — Muddy carpets and soaked furniture lay in moldering piles on the streets of this state capital. It was Sunday morning, Oct. 29, 2017. Eight days earlier, torrents of water had poured off the steep slopes of the island’s central mountain range. Flash floods ripped through neighborhoods. A landslide killed 11 workers at a construction site for a high-rise apartment tower, burying them in mud. It was Penang Island’s second catastrophic deluge in five weeks.

    Kam Suan Pheng, an island resident and one of Malaysia’s most prominent soil scientists, stepped to the microphone in front of 200 people hastily gathered for an urgent forum on public safety. Calmly, as she’s done several times before, Kam explained that the contest between Mother Earth’s increasingly fierce meteorological outbursts and the islanders’ affection for building on steep slopes and replacing water-absorbing forest and farmland with roads and buildings would inevitably lead to more tragedies.

    “When places get urbanized, the sponge gets smaller. So when there is development, the excess rainwater gets less absorbed into the ground and comes off as flash floods,” she said. “The flood situation is bound to worsen if climate change brings more rain and more intense rainfall.”

    Five days later it got worse. Much worse. On Nov. 4, and for the next two days, Penang was inundated by the heaviest rainfall ever recorded on the island. Water flooded streets 3.6 meters (12 feet) deep. Seven people died. The long-running civic discussion that weighed new construction against the risks of increasingly fierce ecological impediments grew more urgent. George Town last year joined an increasing number of the world’s great coastal cities — Houston, New Orleans, New York, Cape Town, Chennai, Jakarta, Melbourne, São Paulo — where the consequences are especially vivid.
    The empty apartment construction site where 11 men died in an October 2017 landslide. Image by Keith Schneider for Mongabay.


    Penang’s state government and Chow Kon Yeow, its new chief minister, recognize the dilemma. Three weeks after being named in May to lead the island, Chow told two reporters from The Star newspaper that “[e]conomic growth with environmental sustainability would be an ideal situation rather than sacrificing the environment for the sake of development.”

    But Chow also favors more growth. He is the lead proponent for building one of the largest and most expensive transportation projects ever undertaken by a Malaysian city: a $11.4 billion scheme that includes an underwater tunnel linking to peninsular Malaysia, three highways, a light rail line, a monorail, and a 4.8-kilometer (3-mile) gondola from the island to the rest of Penang state on the Malay peninsula.

    The state plans to finance construction with proceeds from the sale of 1,800 hectares (4,500 acres) of new land reclaimed from the sea along the island’s southern shore. The Southern Reclamation Project calls for building three artificial islands for manufacturing, retail, offices, and housing for 300,000 residents.

    Awarded rights to build the reclamation project in 2015, the SRS Consortium, the primary contractors, are a group of national and local construction companies awaiting the federal government’s decision to proceed. Island fishermen and their allies in Penang’s community of environmental organizations and residential associations oppose the project, and they proposed a competing transport plan that calls for constructing a streetcar and bus rapid transit network at one-third the cost. (See Mongabay –https://news.mongabay.com/2017/04/is-a-property-boom-in-malaysia-causing-a-fisheries-bust-in-penang/)

    For a time the national government stood with the fishermen. Wan Junaidi Tuanku Jaafar, the former minister of natural resources and environment and a member of Barisan Nasional (BN), the ruling coalition, refused to allow the project. “The 1,800-hectare project is too massive and can change the shoreline in the area,” he told reporters. “It will not only affect the environment but also the forest such as mangroves. Wildlife and marine life, their breeding habitats will be destroyed.”

    The state, and Penang Island, however, have been governed since 2008 by leaders of the Pakatan Harapan coalition, which supported the transport and reclamation mega projects. In May 2018, Pakatan Harapan routed the BN in parliamentary elections. Former prime minister Mahathir Mohamed, the leader of Pakatan Harapan, assumed power once again. Island leaders anticipate that their mega transport and reclamation projects will be approved.

    It is plain, though, that last year’s floods opened a new era of civic reflection and reckoning with growth. Proof is everywhere, like the proliferation of huge blue tarps draped across flood-scarred hillsides outside of George Town’s central business district. Intended to block heavy rain from pushing more mud into apartment districts close by, the blue tarps are a distinct signal of ecological distress.

    Or the flood-damaged construction sites in Tanjung Bungah, a fast-growing George Town suburb. A lone guard keeps visitors from peering through the gates of the empty apartment construction site where 11 men died in the October 2017 landslide. About a mile away, a row of empty, cracked, expensive and never-occupied hillside townhouses are pitched beside a road buckled like an accordion. The retaining wall supporting the road and development collapsed in the November 2017 flood, causing expensive property damage.
  • A row of empty, cracked, expensive and never-occupied hillside townhouses are pitched beside a road buckled like an accordion. The retaining wall supporting the road and development collapsed in a November 2017 flood, causing extensive property damage. Image by Keith Schneider for Mongabay.

    Gurmit Singh, founder and chairman of the Centre for Environment, Technology and Development, Malaysia (CETDEM), and dean of the nation’s conservation activists, called Penang state government’s campaign for more growth and mega infrastructure development “a folly.”

    “It exceeds the carrying capacity of the island. It should never be approved,” he said in an interview in his Kuala Lumpur office.

    Singh, who is in his 70s and still active, was raised on Penang Island. He is an eyewitness to the construction that made much of his boyhood geography unrecognizable. “Everything built there now is unsustainable,” he said.

    It’s taken decades to reach that point. Before 1969, when state authorities turned to Robert Nathan and Associates, a U.S. consultancy, to draw up a master plan for economic development, Penang Island was a 293-square-kilometer (113-square-mile) haven of steep mountain forests, ample rice paddies, and fishing villages reachable only by boat.

    For most residents, though, Penang Island was no tropical paradise. Nearly one out of five working adults was jobless, and poverty was endemic in George Town, its colonial capital, according to national records.

    Nathan proposed a path to prosperity: recruiting electronics manufacturers to settle on the island and export their products globally. His plan emphasized the island’s location on the Strait of Malacca, a trading route popular since the 16th century that tied George Town to Singapore and put other big Asian ports in close proximity.

  • Sea and harbor traffic on the Strait of Malacca. Image by Keith Schneider for Mongabay.

    As a 20th century strategy focused on stimulating the economy, Nathan’s plan yielded real dividends. The island’s population nearly doubled to 755,000, according to national estimates. Joblessness hovers in the 2 percent range.

    Foreign investors poured billions of dollars into manufacturing, retail and residential development, and all the supporting port, energy, road, and water supply and wastewater treatment infrastructure. In 1960, the island’s urbanized area totaled 29.5 square kilometers (11.4 square miles), almost all of it in and immediately surrounding George Town. In 2015, the urban area had spread across 112 square kilometers (43 square miles) and replaced the mangroves, rubber plantations, rice paddies and fishing villages along the island’s northern and eastern coasts.

    There are now 220,000 homes on the island, with more than 10,000 new units added annually, according to National Property Information Center. George Town’s colonial center, which dates to its founding in 1786, was designated a UNESCO World Heritage site in 2008, like Venice and Angkor Wat. The distinction helped George Town evolve into a seaside tourist mecca. The state of Penang, which includes 751 square kilometers (290 square miles) on the Malay peninsula, attracts over 6 million visitors annually, roughly half from outside Malaysia. Most of the visitors head to the island, according to Tourism Malaysia.

    Nathan’s plan, though, did not anticipate the powerful ecological and social responses that runaway shoreline and hillside development would wreak in the 21st century. Traffic congestion in George Town is the worst of any Malaysian city. Air pollution is increasing. Flooding is endemic.

  • Blue tarps drape the steep and muddy hillsides in George Town to slow erosion during heavy rain storms. Image by Keith Schneider for Mongabay.

    Nor in the years since have Penang’s civic authorities adequately heeded mounting evidence of impending catastrophes, despite a series of government-sponsored reports calling for economic and environmental sustainability.

    Things came to a head late last year. Flooding caused thousands of people to be evacuated from their homes. Water tore at hillsides, opening the forest to big muddy wounds the color of dried blood. Never had Penang Island sustained such damage from storms that have become more frequent, according to meteorological records. Rain in November that measured over 400 millimeters (13 inches) in a day. The damage and deaths added fresh urgency and new recruits to Penang Island’s longest-running civic argument: Had the island’s growth become a hazard to life?

    George Town is far from alone in considering the answer. The 20th century-inspired patterns of rambunctious residential, industrial and infrastructure development have run headlong into the ferocious meteorological conditions of the 21st century. Coastal cities, where 60 percent of the world’s people live, are being challenged like never before by battering storms and deadly droughts. For instance, during a two-year period that ended in 2016, Chennai, India, along the Bay of Bengal, was brutalized by a typhoon and floods that killed over 400 people, and by a drought that prompted deadly protests over water scarcity. Houston drowned in a storm. Cape Town is in the midst of a two-year drought emergency.

    George Town last year joined the expanding list of cities forced by Nature to a profound reckoning. Between 2013 and mid-October 2017, according to state records, Penang recorded 119 flash floods. The annual incidence is increasing: 22 in 2013; 30 in 2016. Residents talk about a change in weather patterns for an island that once was distinguished by a mild and gentle climate but is now experiencing much more powerful storms with cyclone-force winds and deadly rain.

    Billions of dollars in new investment are at stake. Apartment towers in the path of mudslides and flash flooding rise on the north shore near George Town. Fresh timber clearing continues apace on the steep slopes of the island’s central mountain range, despite regulations that prohibit such activity. Demographers project that the island’s population could reach nearly 1 million by mid-century. That is, if the monstrous storms don’t drive people and businesses away — a trend that has put Chennai’s new high-tech corridor at risk.

    The urgency of the debate has pushed new advocates to join Kam Suan Pheng at the forefront of Penang Island’s environmental activism. One of them is Andrew Ng Yew Han, a 34-year-old teacher and documentary filmmaker whose “The Hills and the Sea” describes how big seabed reclamation projects on the island’s north end have significantly diminished fish stocks and hurt fishing villages. High-rise towers are swiftly pushing a centuries-old way of life out of existence. The same could happen to the more than 2,000 licensed fishermen and women contending with the much bigger reclamation proposals on the south coast.

    “How are they going to survive?” Han said in an interview. “This generation of fisherman will be wiped out. None of their kids want to be fisherman. Penang is holding a world fisherman conference in 2019. The city had the gall to use a picture of local fisherman as the poster. No one who’s coming here knows, ‘Hey you are reclaiming land and destroying livelihood of an entire fishing village.’”

    “We all want Penang to be progressive. To grow. To become a great city,” he adds on one of his videos. “But at whose expense? That’s the question. That’s the story I’m covering.”

  • Andrew Ng Yew Han, a 34-year-old teacher and documentary film maker whose “The Hills and the Sea” describes how big seabed reclamation projects on the island’s north end have significantly diminished fish stocks and hurt fishing villages. Image by Keith Schneider for Mongabay.

    Another young advocate for sustainable growth is Rexy Prakash Chacko, a 26-year-old engineer documenting illegal forest clearing. Chacko is an active participant in the Penang Forum, the citizens’ group that held the big meeting on flooding last October. Nearly two years ago, he helped launch Penang Hills Watch, an online site that uses satellite imagery and photographs from residents to identify and map big cuts in the Penang hills — cuts that are illegal according to seldom-enforced state and federal laws.

    Kam Suan Pheng and other scientists link the hill clearing to the proliferation of flash flooding and extensive landslides that occur on the island now, even with moderate rainfall. In 1960, Malaysia anticipated a future problem with erosion when it passed the Land Conservation Act that designated much of Penang Island’s mountain forests off-limits to development. In 2007, Penang state prohibited development on slopes above an elevation of 76 meters (250 feet), and any slope with an incline greater than 25 degrees, or 47 percent.

    Images on Penang Hills Watch make it plainly apparent that both measures are routinely ignored. In 2015, the state confirmed as much when it made public a list of 55 blocks of high-rise housing, what the state called “special projects,” that had been built on hillsides above 76 meters or on slopes steeper than 25 degrees. The “special projects” encompassed 10,000 residences and buildings as tall as 45 stories.

  • Rexy Prakash Chacko, a 26-year-old engineer who helped launch Penang Hills Watch, an online site that uses satellite imagery and photographs from residents to identify and map big cuts in the Penang hills. Image by Keith Schneider for Mongabay.

    “There is a lot of water coming down the hills now,” Chacko said in an interview. “It’s a lack of foresight. Planning has to take into account what happens when climate change is a factor. Clearing is happening. And in the last two years the rain is getting worse.

    “You can imagine. People are concerned about this. There was so much lost from the water and the mud last year.”

    Ignoring rules restricting development has consequences, as Kam Suan Pheng has pointed out since getting involved in the civic discussion about growth in 2015. After the October 2017 landslide, she noted that local officials insisted the apartment building where the 11 deaths occurred was under construction on flat ground. But, she told Mongabay, an investigation by the State Commission of Inquiry (SCI) found that the apartment construction site abutted a 60-degree slope made of granite, which is notoriously unstable when it becomes rain-saturated.

    “State authorities continued to insist that development above protected hill land is prohibited,” Kam said in an email. “There is little to show that more stringent enforcement on hill slope development has been undertaken. Hopefully the findings of the SCI will serve as lessons for more stringent monitoring and enforcement of similar development projects so that the 11 lives have not been sacrificed in vain.”



  • The market for hillside residential development is strong in George Town despite the more intense storms. Image by Keith Schneider for Mongabay.

    By Keith Schneider

    Mongabay Series: Southeast Asian infrastructure

    Related News:
  • Housing conundrum for the young and developers - Business News ...


    Related posts::
  • Hills, landslides, floods and damaged houses: What to do? 

     

    Penang floods and landslides, looking beyound natural causes!

     

    IJM hill clearing & Trehaus construction damaged nearby houses since 2014 must be mitigated quickly!

     

    Penang landslides & flooding are natural disasters man-made?

     

    Absorb New ways to prevent floods

     

    Make environment our 2018 priority

    Penang hit by floods again !

     

    Penang govt rapped over hill slope development

     

     

  • Has Penang Island’s growth & development become a hazard to life?



  • Malaysia’s Penang Island has undergone massive development since the 1960s, a process that continues today with plans for transit and land-reclamation megaprojects.

  • The island is increasingly facing floods and landslides, problems environmentalists link to paving land and building on steep slopes.

  • This is the second in a six-part series of articles on infrastructure projects in Peninsular Malaysia.

    GEORGE TOWN, Malaysia — Muddy carpets and soaked furniture lay in moldering piles on the streets of this state capital. It was Sunday morning, Oct. 29, 2017. Eight days earlier, torrents of water had poured off the steep slopes of the island’s central mountain range. Flash floods ripped through neighborhoods. A landslide killed 11 workers at a construction site for a high-rise apartment tower, burying them in mud. It was Penang Island’s second catastrophic deluge in five weeks.

    Kam Suan Pheng, an island resident and one of Malaysia’s most prominent soil scientists, stepped to the microphone in front of 200 people hastily gathered for an urgent forum on public safety. Calmly, as she’s done several times before, Kam explained that the contest between Mother Earth’s increasingly fierce meteorological outbursts and the islanders’ affection for building on steep slopes and replacing water-absorbing forest and farmland with roads and buildings would inevitably lead to more tragedies.

    “When places get urbanized, the sponge gets smaller. So when there is development, the excess rainwater gets less absorbed into the ground and comes off as flash floods,” she said. “The flood situation is bound to worsen if climate change brings more rain and more intense rainfall.”

    Five days later it got worse. Much worse. On Nov. 4, and for the next two days, Penang was inundated by the heaviest rainfall ever recorded on the island. Water flooded streets 3.6 meters (12 feet) deep. Seven people died. The long-running civic discussion that weighed new construction against the risks of increasingly fierce ecological impediments grew more urgent. George Town last year joined an increasing number of the world’s great coastal cities — Houston, New Orleans, New York, Cape Town, Chennai, Jakarta, Melbourne, São Paulo — where the consequences are especially vivid.
    The empty apartment construction site where 11 men died in an October 2017 landslide. Image by Keith Schneider for Mongabay.


    Penang’s state government and Chow Kon Yeow, its new chief minister, recognize the dilemma. Three weeks after being named in May to lead the island, Chow told two reporters from The Star newspaper that “[e]conomic growth with environmental sustainability would be an ideal situation rather than sacrificing the environment for the sake of development.”

    But Chow also favors more growth. He is the lead proponent for building one of the largest and most expensive transportation projects ever undertaken by a Malaysian city: a $11.4 billion scheme that includes an underwater tunnel linking to peninsular Malaysia, three highways, a light rail line, a monorail, and a 4.8-kilometer (3-mile) gondola from the island to the rest of Penang state on the Malay peninsula.

    The state plans to finance construction with proceeds from the sale of 1,800 hectares (4,500 acres) of new land reclaimed from the sea along the island’s southern shore. The Southern Reclamation Project calls for building three artificial islands for manufacturing, retail, offices, and housing for 300,000 residents.

    Awarded rights to build the reclamation project in 2015, the SRS Consortium, the primary contractors, are a group of national and local construction companies awaiting the federal government’s decision to proceed. Island fishermen and their allies in Penang’s community of environmental organizations and residential associations oppose the project, and they proposed a competing transport plan that calls for constructing a streetcar and bus rapid transit network at one-third the cost. (See Mongabay –https://news.mongabay.com/2017/04/is-a-property-boom-in-malaysia-causing-a-fisheries-bust-in-penang/)

    For a time the national government stood with the fishermen. Wan Junaidi Tuanku Jaafar, the former minister of natural resources and environment and a member of Barisan Nasional (BN), the ruling coalition, refused to allow the project. “The 1,800-hectare project is too massive and can change the shoreline in the area,” he told reporters. “It will not only affect the environment but also the forest such as mangroves. Wildlife and marine life, their breeding habitats will be destroyed.”

    The state, and Penang Island, however, have been governed since 2008 by leaders of the Pakatan Harapan coalition, which supported the transport and reclamation mega projects. In May 2018, Pakatan Harapan routed the BN in parliamentary elections. Former prime minister Mahathir Mohamed, the leader of Pakatan Harapan, assumed power once again. Island leaders anticipate that their mega transport and reclamation projects will be approved.

    It is plain, though, that last year’s floods opened a new era of civic reflection and reckoning with growth. Proof is everywhere, like the proliferation of huge blue tarps draped across flood-scarred hillsides outside of George Town’s central business district. Intended to block heavy rain from pushing more mud into apartment districts close by, the blue tarps are a distinct signal of ecological distress.

    Or the flood-damaged construction sites in Tanjung Bungah, a fast-growing George Town suburb. A lone guard keeps visitors from peering through the gates of the empty apartment construction site where 11 men died in the October 2017 landslide. About a mile away, a row of empty, cracked, expensive and never-occupied hillside townhouses are pitched beside a road buckled like an accordion. The retaining wall supporting the road and development collapsed in the November 2017 flood, causing expensive property damage.
  • A row of empty, cracked, expensive and never-occupied hillside townhouses are pitched beside a road buckled like an accordion. The retaining wall supporting the road and development collapsed in a November 2017 flood, causing extensive property damage. Image by Keith Schneider for Mongabay.

    Gurmit Singh, founder and chairman of the Centre for Environment, Technology and Development, Malaysia (CETDEM), and dean of the nation’s conservation activists, called Penang state government’s campaign for more growth and mega infrastructure development “a folly.”

    “It exceeds the carrying capacity of the island. It should never be approved,” he said in an interview in his Kuala Lumpur office.

    Singh, who is in his 70s and still active, was raised on Penang Island. He is an eyewitness to the construction that made much of his boyhood geography unrecognizable. “Everything built there now is unsustainable,” he said.

    It’s taken decades to reach that point. Before 1969, when state authorities turned to Robert Nathan and Associates, a U.S. consultancy, to draw up a master plan for economic development, Penang Island was a 293-square-kilometer (113-square-mile) haven of steep mountain forests, ample rice paddies, and fishing villages reachable only by boat.

    For most residents, though, Penang Island was no tropical paradise. Nearly one out of five working adults was jobless, and poverty was endemic in George Town, its colonial capital, according to national records.

    Nathan proposed a path to prosperity: recruiting electronics manufacturers to settle on the island and export their products globally. His plan emphasized the island’s location on the Strait of Malacca, a trading route popular since the 16th century that tied George Town to Singapore and put other big Asian ports in close proximity.

  • Sea and harbor traffic on the Strait of Malacca. Image by Keith Schneider for Mongabay.

    As a 20th century strategy focused on stimulating the economy, Nathan’s plan yielded real dividends. The island’s population nearly doubled to 755,000, according to national estimates. Joblessness hovers in the 2 percent range.

    Foreign investors poured billions of dollars into manufacturing, retail and residential development, and all the supporting port, energy, road, and water supply and wastewater treatment infrastructure. In 1960, the island’s urbanized area totaled 29.5 square kilometers (11.4 square miles), almost all of it in and immediately surrounding George Town. In 2015, the urban area had spread across 112 square kilometers (43 square miles) and replaced the mangroves, rubber plantations, rice paddies and fishing villages along the island’s northern and eastern coasts.

    There are now 220,000 homes on the island, with more than 10,000 new units added annually, according to National Property Information Center. George Town’s colonial center, which dates to its founding in 1786, was designated a UNESCO World Heritage site in 2008, like Venice and Angkor Wat. The distinction helped George Town evolve into a seaside tourist mecca. The state of Penang, which includes 751 square kilometers (290 square miles) on the Malay peninsula, attracts over 6 million visitors annually, roughly half from outside Malaysia. Most of the visitors head to the island, according to Tourism Malaysia.

    Nathan’s plan, though, did not anticipate the powerful ecological and social responses that runaway shoreline and hillside development would wreak in the 21st century. Traffic congestion in George Town is the worst of any Malaysian city. Air pollution is increasing. Flooding is endemic.

  • Blue tarps drape the steep and muddy hillsides in George Town to slow erosion during heavy rain storms. Image by Keith Schneider for Mongabay.

    Nor in the years since have Penang’s civic authorities adequately heeded mounting evidence of impending catastrophes, despite a series of government-sponsored reports calling for economic and environmental sustainability.

    Things came to a head late last year. Flooding caused thousands of people to be evacuated from their homes. Water tore at hillsides, opening the forest to big muddy wounds the color of dried blood. Never had Penang Island sustained such damage from storms that have become more frequent, according to meteorological records. Rain in November that measured over 400 millimeters (13 inches) in a day. The damage and deaths added fresh urgency and new recruits to Penang Island’s longest-running civic argument: Had the island’s growth become a hazard to life?

    George Town is far from alone in considering the answer. The 20th century-inspired patterns of rambunctious residential, industrial and infrastructure development have run headlong into the ferocious meteorological conditions of the 21st century. Coastal cities, where 60 percent of the world’s people live, are being challenged like never before by battering storms and deadly droughts. For instance, during a two-year period that ended in 2016, Chennai, India, along the Bay of Bengal, was brutalized by a typhoon and floods that killed over 400 people, and by a drought that prompted deadly protests over water scarcity. Houston drowned in a storm. Cape Town is in the midst of a two-year drought emergency.

    George Town last year joined the expanding list of cities forced by Nature to a profound reckoning. Between 2013 and mid-October 2017, according to state records, Penang recorded 119 flash floods. The annual incidence is increasing: 22 in 2013; 30 in 2016. Residents talk about a change in weather patterns for an island that once was distinguished by a mild and gentle climate but is now experiencing much more powerful storms with cyclone-force winds and deadly rain.

    Billions of dollars in new investment are at stake. Apartment towers in the path of mudslides and flash flooding rise on the north shore near George Town. Fresh timber clearing continues apace on the steep slopes of the island’s central mountain range, despite regulations that prohibit such activity. Demographers project that the island’s population could reach nearly 1 million by mid-century. That is, if the monstrous storms don’t drive people and businesses away — a trend that has put Chennai’s new high-tech corridor at risk.

    The urgency of the debate has pushed new advocates to join Kam Suan Pheng at the forefront of Penang Island’s environmental activism. One of them is Andrew Ng Yew Han, a 34-year-old teacher and documentary filmmaker whose “The Hills and the Sea” describes how big seabed reclamation projects on the island’s north end have significantly diminished fish stocks and hurt fishing villages. High-rise towers are swiftly pushing a centuries-old way of life out of existence. The same could happen to the more than 2,000 licensed fishermen and women contending with the much bigger reclamation proposals on the south coast.

    “How are they going to survive?” Han said in an interview. “This generation of fisherman will be wiped out. None of their kids want to be fisherman. Penang is holding a world fisherman conference in 2019. The city had the gall to use a picture of local fisherman as the poster. No one who’s coming here knows, ‘Hey you are reclaiming land and destroying livelihood of an entire fishing village.’”

    “We all want Penang to be progressive. To grow. To become a great city,” he adds on one of his videos. “But at whose expense? That’s the question. That’s the story I’m covering.”

  • Andrew Ng Yew Han, a 34-year-old teacher and documentary film maker whose “The Hills and the Sea” describes how big seabed reclamation projects on the island’s north end have significantly diminished fish stocks and hurt fishing villages. Image by Keith Schneider for Mongabay.

    Another young advocate for sustainable growth is Rexy Prakash Chacko, a 26-year-old engineer documenting illegal forest clearing. Chacko is an active participant in the Penang Forum, the citizens’ group that held the big meeting on flooding last October. Nearly two years ago, he helped launch Penang Hills Watch, an online site that uses satellite imagery and photographs from residents to identify and map big cuts in the Penang hills — cuts that are illegal according to seldom-enforced state and federal laws.

    Kam Suan Pheng and other scientists link the hill clearing to the proliferation of flash flooding and extensive landslides that occur on the island now, even with moderate rainfall. In 1960, Malaysia anticipated a future problem with erosion when it passed the Land Conservation Act that designated much of Penang Island’s mountain forests off-limits to development. In 2007, Penang state prohibited development on slopes above an elevation of 76 meters (250 feet), and any slope with an incline greater than 25 degrees, or 47 percent.

    Images on Penang Hills Watch make it plainly apparent that both measures are routinely ignored. In 2015, the state confirmed as much when it made public a list of 55 blocks of high-rise housing, what the state called “special projects,” that had been built on hillsides above 76 meters or on slopes steeper than 25 degrees. The “special projects” encompassed 10,000 residences and buildings as tall as 45 stories.

  • Rexy Prakash Chacko, a 26-year-old engineer who helped launch Penang Hills Watch, an online site that uses satellite imagery and photographs from residents to identify and map big cuts in the Penang hills. Image by Keith Schneider for Mongabay.

    “There is a lot of water coming down the hills now,” Chacko said in an interview. “It’s a lack of foresight. Planning has to take into account what happens when climate change is a factor. Clearing is happening. And in the last two years the rain is getting worse.

    “You can imagine. People are concerned about this. There was so much lost from the water and the mud last year.”

    Ignoring rules restricting development has consequences, as Kam Suan Pheng has pointed out since getting involved in the civic discussion about growth in 2015. After the October 2017 landslide, she noted that local officials insisted the apartment building where the 11 deaths occurred was under construction on flat ground. But, she told Mongabay, an investigation by the State Commission of Inquiry (SCI) found that the apartment construction site abutted a 60-degree slope made of granite, which is notoriously unstable when it becomes rain-saturated.

    “State authorities continued to insist that development above protected hill land is prohibited,” Kam said in an email. “There is little to show that more stringent enforcement on hill slope development has been undertaken. Hopefully the findings of the SCI will serve as lessons for more stringent monitoring and enforcement of similar development projects so that the 11 lives have not been sacrificed in vain.”



  • The market for hillside residential development is strong in George Town despite the more intense storms. Image by Keith Schneider for Mongabay.

    By Keith Schneider

    Mongabay Series: Southeast Asian infrastructure

    Related News:
  • Housing conundrum for the young and developers - Business News ...


    Related posts::
  • Hills, landslides, floods and damaged houses: What to do? 

     

    Penang floods and landslides, looking beyound natural causes!

     

    IJM hill clearing & Trehaus construction damaged nearby houses since 2014 must be mitigated quickly!

     

    Penang landslides & flooding are natural disasters man-made?

     

    Absorb New ways to prevent floods

     

    Make environment our 2018 priority

    Penang hit by floods again !

     

    Penang govt rapped over hill slope development

     

     

  • Monday, January 29, 2018

    Absorb New ways to prevent floods

    Sponge City: Solutions for China's Thirsty & Flooded cities

     China's 'sponge city' projects may be worthwhile examples for Malaysia.


    "Only about 20~30% of rainwater infiltrates the ground in urban areas, so it breaks the naturual water circulation.- Wen Mei Dubbelaar"

    Last week, it was the turn of Petaling Jaya, Gombak and Sungai Buloh to be the latest major urban areas in Malaysia to suffer flash floods (Flash floods wreak havoc in PJ - Nation). Scenes of cars and buildings submerged in muddy water are now almost an everyday thing. The focus should now shift from the bad situations to the solutions.

    It was also last week that I attended a briefing organised by civil society groups for Penang and Seberang Perai municipal officials and members. The briefing was on the recent floods.

    Later, I came across several articles on how China is turning 30 of its flood-prone areas into “sponge cities” to prevent floods and retain rainwater.

    The Chinese plan big and fast. It launched the sponge city project only in 2015, but it aims to retain 70% of rain in 80% of urban areas by 2020. The sponge concept is set to spread rapidly as part of global efforts to reduce the impact of increased rainfall and floods, and climate change.

    The concept figured prominently at the briefing chaired by Penang state exco member Chow Kon Yeow. Scientist Dr Kam Suan Pheng introduced it when explaining the floods.

    She contrasted the present situation when rain falls with what used to happen. In the past, 50% of the rain seeped through the natural ground cover (trees, grass, etc) and into the ground. There was 10% water runoff (to rivers and drains) and 40% evapotranspiration (water going back to the atmosphere).

    The trees and green spaces act as a sponge to absorb the rainwater that infiltrates the soil, preventing the water from building up into flash floods.

    Due to urbanisation, the green spaces have been paved over with cement and concrete. Now, only 15% of the rain infiltrates the soil, while the runoff has increased to 55% and evapotranspiration is 30%. The sponge now absorbs 15% of the rainwater compared to the previous 50%.

    Dr Kam quoted former Penang Water Authority general manager Kam U-Tee as saying that the October 2008 Penang floods were caused by conversion of the valleys into “concrete aprons that do not retain water”. As a result, the water immediately flowed into streams, causing flash floods, even with moderate rainfall.

    Given this analysis, a key part of tackling the floods is to reverse the loss of the sponge. In recent decades, Malaysia has seen the conversion of a lot of farms, parks, trees and grass areas into concrete jungles of roads, houses, commercial buildings and car parks.

    There now has to be high sensitivity to the valuable environmental and economic roles of trees, gardens, fields and grasslands, and parks. The aim of garden cities is not just to be pleasing to the eye but to be a very important part of development as well.

    Now comes the role of sponge cities. The world is applauding the Chinese initiative to counter floods and improve water security by building up the natural cover (or sponge) in its cities.

    In 2010, landslides during flooding killed 700 in three quarters of China’s provinces. Last year, rains flooded southern China, destroying homes and killing around 60 people.

    In 2015, China launched the Sponge City initiative, which now covers 30 cities, including Shanghai, Xiamen and Wuhan. The target: by 2020, 80% of its urban areas will absorb and re-use 70% of rainwater.

    The many types of projects include:

    • > Constructing permeable roads that enable water to infiltrate the ground;
    • > Replacing pavements on roads and parks to make them permeable;
    • > Building wetlands to absorb and store rainwater;
    • > Constructing rooftop gardens (for example, 4.3 million square feet in Shanghai);
    • > Plant trees on streets and public squares;
    • > Build community gardens and parks to expand green spaces; and
    • > Build manmade lakes and preserve agricultural land to hold water.

    “In the natural environment, most precipitation infiltrates the ground or is received by surface water, but this is disrupted when there are large-scale hard pavements,” said Wen Mei Dubbelaar, water management director at China Arcadis, in words similar to Dr Kam’s.

    “Now only about 20-30% of rainwater infiltrates the ground in urban areas, so it breaks the natural water circulation and causes water logging and surface water pollution,” said Wen in an interview with The Guardian.

    In Shanghai’s Lingang district, the streets are built with permeable pavements. There are rain gardens filled with soil and plants, buildings feature green rooftops and water tanks, and a manmade lake controls water flows, reports The Guardian.

    Prof Hui Li at Tongji University said the first thing is to preserve or restore natural waterways as that is the natural way to reduce flooding risk.

    The problem in Wuhan is that a lot of small rivers were filled in during building. But Lingang still has agriculture land and a lake to hold more water during heavy rain.

    What about the cost factor? So far the cities have received over US$12bil (RM47.4bil) for sponge projects. The central government funds 15-20% of costs, and the rest is from local governments and private developers.

    But compare this to the US$100bil (RM395bil) of direct economic losses due to floods in China between 2011 and 2014, plus the human lives lost.

    Sponge cities are the way to go for the future. Our own governments – federal, state and municipal – should study this option seriously, as the public braces itself for more floods ahead.

    - Global Trends by Martin Khor

    Martin Khor is executive director of the South Centre. The views expressed here are entirely his own.


    Related Links

    China's Sponge City: Flooding Solutions

     

    10 measures to prevent (urban) flooding - Wavin

     

    Related posts:


    Our Environment is Our Life - YouTube THE year has barely started, and already we have so many reports of weather and climate-related e...

    Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl...


    Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'...

    PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development Becoming bald: A view of the clearing work seen at Bukit Relau which was visible from the Penang Bridge in November last year. GEORGE..


    Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..


    https://youtu.be/kslhytLg-Wc Hills, landslides and floods: What to do?   The mega floods in Penang which followed the landslide...

    https://youtu.be/yqtdkBsipCU Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s..