MBPP, contractor, engineers and DOSH named as responsible in fatal Penang landslide

https://youtu.be/R07RRPADcK0

https://www.thestar.com.my/news/nation/2019/02/14/landslide-report-blames-contractor-mbpp-and-dosh/?jwsource=cl

Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer. NSTP/MIKAIL ONG
MBPP among four named as responsible in fatal Penang landslide

GEORGE TOWN: Four parties have been identified as being responsible for the fatal landslide at the construction site of the paired road at Jalan Bukit Kukus last October incident, including the Penang Island City Council (MBPP).

A special investigation committee set up by the Penang government following the fatal landslide at the construction site also named the other three parties, namely the contractor Yuta Maju Sdn Bhd, the consultant, Jurutera Perunding GEA (M) Sdn Bhd and the independent checking engineer G&P Professional Sdn Bhd.

Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer.

“By appointing Jurutera Perunding GEA, it does not mean that the council is free from responsibilities to ensure the success of the project from all aspects.

"As such, any actions to be taken against the council will depend on the outcome of investigations by the police, the Department of Occupational Safety and Heath (DOSH) and the Construction Industry Development Board (CIDB) into the incident," he said when making public findings of the investigation committee.

Ahmad Zakiyuddin said as for Yuta Maju, it had failed to ensure satisfactory mitigation works at the project site, and that the temporary slope constructed at the project site was not endorsed or designed by accredited consultants, which was a violation of the Board of Engineers Malaysia (BEM) guidelines.

“It also failed to ensure site safety by removing the empty containers at the project site, where nine bodies were recovered," he added.

As for Jurutera Perunding GEA, Ahmad Zakiyuddin said the party had failed to ensure that the contractor abide by the guidelines set out by the BEM, while G&P Professional had failed to abide by the job scope given by the council.

“Following our findings, we have recommended that the contractor, consultant and independent checking engineer be blacklisted from any tender consideration for projects in the future.

“That said, they will still have to continue their works for the paired road project, until the project completion, slated for May next year,” he added.

The landslide at the Bukit Kukus paired roads project site on Oct 19 last year killed nine site workers and left four others injured.

The search and rescue (SAR) operation was called off after five days. The project's stop-work orders, separately issued by DOSH, CIDB and the council, were lifted up recently.

Ahmad Zakiyuddin said the special investigation committee also identified 10 main factors which had contributed the to fatal landslide, particularly not fully adopting best practices in construction work.

Other factors included:

* heavy rain on the morning of the incident at 55mm

* the contractor was unable to enter the project site to carry out mitigation works as stop-work order was issued by DOSH two days prior to the incident following a worksite accident

* unsafe construction processes

* failure to recognise the significance of an earlier incident (falling beams at another part of the project site two days prior to the landslide);

* lack of supervision

* failure to identify risk due to the change of process

* lack of comprehensive inspection and testing

* failure in risk communication

* poor management of sub-contractors.

Asked on why the services of the contractor, consultant and independent checking engineer were not immediately terminated following the incident, Ahmad Zakiyuddin said from what he understood, the stop-work orders issued on the three were only for one part of the project and not the entire project.

"Also, there was no record of safety issues prior to the landslide," he said.

He called on efforts to protect the remaining part of the project as a resu

lt of a negative perception.

"Any delay will put the project at greater risks."

To another question if the special investigation committee's findings would be made public, he there had been no plans to do so as the report served as a guideline for the state. - By Audrey Dermawan, NST >


‘MBPP hired resident engineer for Bukit Kukus project’

GEORGE TOWN: The Penang Island City Council (MBPP) appointed a resident engineer and an independent checking engineer even before the start of the Bukit Kukus paired road project, says Chief Minister Chow Kon Yeow.

“If you see the action taken by MBPP, they understand their technical insufficiency in terms of a geotechnical engineer. That’s why in the contract, they required the main contractor to appoint a resident engineer, who was paid by MBPP to monitor the project on MBPP’s behalf.

“The independent checking engineers were also paid by MBPP. So, it was a measure taken by MBPP even before the start of the project, knowing that this is a big project.

“They did not have the capacity to monitor the project as they have only two or three engineers who have to be looking at other matters besides this project.

“So, they took action to appoint a resident engineer as well as independent checking enginners to act on behalf of MBPP,” he told reporters at the Penang Development Corp­oration Chinese New Year celebration at the PDC office in Bayan Lepas yesterday.

Chow also said the state would wait for the Department of Occupational Safety and Health (DOSH) report first.

“We will leave it to DOSH’s findings. Let DOSH come out with the report and we will take the necessary action after that,” he said.

Asked if MBPP had to bear necessary compensation for families of the victims of the landslide last October, Chow said MBPP had not received any claim so far.

Chow was asked to respond to the Con­sumers Association of Penang’s (CAP) call for stern action to be taken against the wrongdoers responsible for the tragedy.

CAP president S.M. Mohamed Idris in a statement yesterday said: “While we welcome the investigation committee’s findings as to who is responsible for the tragedy, we are concerned that apart from recommending the blacklisting of the contractor, consultant and independent checking engineer from any tender consideration for future projects, it appears that no further stern action has been recommended.

“In particular, we want to know what action will be taken against MBPP,” he said.

Deputy Chief Minister I Datuk Ahmad Zaki­yuddin Abdul Rahman, who headed the investigation panel, was reported yesterday as saying that MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired road project had not adhered to construction and engineering best practices.

Meanwhile, MBPP acknowledged responsibility for the Bukit Kukus landslide tragedy as it is the council’s project.

MBPP mayor Datuk Yew Tung Seang said the council was not pushing away any responsibility or negative comments on the council and project, and that it would be taken seriously. - By Cavina Lim and Intan Amalina Mohd Ali, The Star

Penang landslide report blames contractor, MBPP and DOSH

The special investigative panel report on the Bukit Kukus landslide had not been made public, but excerpts of the findings were made available by the state.

However, it has raised more questions than answers as the state blamed the contractor, Penang Island City Council (MBPP) and the Department of Occupational Safety and Health (DOSH).

In an immediate response, DOSH Penang director Jaafar Leman denied the department was to be blamed for the landslide.

“We were not even invited to be part of the investigative panel to give our views. How could we be blamed?” he asked.

According to the statement by Deputy Chief Minister 1 Datuk Ahmad Zakiyuddin Abdul Rahman who headed the investigative panel, the stop-work order on Oct 17 prevented contractors from entering the site to do maintenance works.

As a result, the temporary toe drain overflowed and water was retained on the reclaimed land contributing to the collapse of the slopes.

“How could a stop order which was issued on Oct 17 contribute to the landslide which occurred on Oct 19?” asked Jaafar.

He said the slopes would have been risky from the beginning as the contractor did not do any mitigation works to strengthen them and it does not make sense to blame DOSH.

The stop-work order was issued on Oct 17 after 14 beams fell in a ravine.

Earlier, during a press conference, Ahmad Zakiyuddin said MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired roads project, had not adhered to construction and engineering best practices.

“The landslide was caused by many factors, which included a temporary construction of a platform to place machinery which was not constructed properly. The temporary platform was created to allow heavy vehicles lift beams for the paired road project.

“MBPP, as owners of the project, had failed to ensure all the hired parties carried out their job.

“MBPP had failed to hire a professional engineer for temporary works to design and supervise the site,” he said yesterday.

Ahmad Zakiyuddin said another factor was the downpour in the morning of the day of the landslide.- The Star


Related News

Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide tragedy. The inquiry still begs a lot of questions, e.g. why was the contract given to Yuta Maju from Terengganu? Could the accident have been prevented if a proper EIA was done? It is not just a "bureaucratic hurdle" but supposed to identify risks and advise mitigation. If the authorities wish to go on with the project, it is not too late to commissi...
See more

 “This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.

“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.
Metro News14 Jan 2019


Bukit Kukus road project illegal, says consumer group | Free Malaysia ..

 

Penang blacklists contractor, engineers in Bukit Kukus road project ...

 

Groups demand Penang govt release Bukit Kukus landslide probe ...

 

Bukit Kukus project to proceed with extra caution - Nation



Related Posts:

Action taken over irregularities at Bukit Kukus paired road project Penang

 

Soil erosion mitigation plans ignored, waters from stream identified as main cause !

 

Penang Landslide occured days after remedial works started

 

Penang landslides & flooding are natural disasters man-made?

 

 Call for action on flooding solution

 

Structural defects to blame, stop history repeating itself !

 

 Fake Awards Scam for Penang Island City Council, Seberang Perai Municipal Council !

 
Dubious honours: (Above) Former Penang Island City Council mayor Patahiyah Ismail with the trophy and certificate for Best Municipal Manager awards in 2013 while her Seberang Prai counterpart Maimunah (pictured here with the Chief Minister Lim Guan Eng and his aide Wong Hon Wai) received the same latter award in 2014

  Malaysian Public varsities, companies, GLC execs also recipients of EBA fake awards

 

MBPP, contractor, engineers and DOSH named as responsible in fatal Penang landslide

https://youtu.be/R07RRPADcK0

https://www.thestar.com.my/news/nation/2019/02/14/landslide-report-blames-contractor-mbpp-and-dosh/?jwsource=cl

Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer. NSTP/MIKAIL ONG
MBPP among four named as responsible in fatal Penang landslide

GEORGE TOWN: Four parties have been identified as being responsible for the fatal landslide at the construction site of the paired road at Jalan Bukit Kukus last October incident, including the Penang Island City Council (MBPP).

A special investigation committee set up by the Penang government following the fatal landslide at the construction site also named the other three parties, namely the contractor Yuta Maju Sdn Bhd, the consultant, Jurutera Perunding GEA (M) Sdn Bhd and the independent checking engineer G&P Professional Sdn Bhd.

Deputy Chief Minister I Datuk Ahmad Zakiyuddin Abdul Rahman, who is the committee chairman, said the MBPP as the owner of the project had failed in its overall responsibility to supervise the project despite having appointed Jurutera Perunding GEA as representative of the superintendent officer.

“By appointing Jurutera Perunding GEA, it does not mean that the council is free from responsibilities to ensure the success of the project from all aspects.

"As such, any actions to be taken against the council will depend on the outcome of investigations by the police, the Department of Occupational Safety and Heath (DOSH) and the Construction Industry Development Board (CIDB) into the incident," he said when making public findings of the investigation committee.

Ahmad Zakiyuddin said as for Yuta Maju, it had failed to ensure satisfactory mitigation works at the project site, and that the temporary slope constructed at the project site was not endorsed or designed by accredited consultants, which was a violation of the Board of Engineers Malaysia (BEM) guidelines.

“It also failed to ensure site safety by removing the empty containers at the project site, where nine bodies were recovered," he added.

As for Jurutera Perunding GEA, Ahmad Zakiyuddin said the party had failed to ensure that the contractor abide by the guidelines set out by the BEM, while G&P Professional had failed to abide by the job scope given by the council.

“Following our findings, we have recommended that the contractor, consultant and independent checking engineer be blacklisted from any tender consideration for projects in the future.

“That said, they will still have to continue their works for the paired road project, until the project completion, slated for May next year,” he added.

The landslide at the Bukit Kukus paired roads project site on Oct 19 last year killed nine site workers and left four others injured.

The search and rescue (SAR) operation was called off after five days. The project's stop-work orders, separately issued by DOSH, CIDB and the council, were lifted up recently.

Ahmad Zakiyuddin said the special investigation committee also identified 10 main factors which had contributed the to fatal landslide, particularly not fully adopting best practices in construction work.

Other factors included:

* heavy rain on the morning of the incident at 55mm

* the contractor was unable to enter the project site to carry out mitigation works as stop-work order was issued by DOSH two days prior to the incident following a worksite accident

* unsafe construction processes

* failure to recognise the significance of an earlier incident (falling beams at another part of the project site two days prior to the landslide);

* lack of supervision

* failure to identify risk due to the change of process

* lack of comprehensive inspection and testing

* failure in risk communication

* poor management of sub-contractors.

Asked on why the services of the contractor, consultant and independent checking engineer were not immediately terminated following the incident, Ahmad Zakiyuddin said from what he understood, the stop-work orders issued on the three were only for one part of the project and not the entire project.

"Also, there was no record of safety issues prior to the landslide," he said.

He called on efforts to protect the remaining part of the project as a resu

lt of a negative perception.

"Any delay will put the project at greater risks."

To another question if the special investigation committee's findings would be made public, he there had been no plans to do so as the report served as a guideline for the state. - By Audrey Dermawan, NST >


‘MBPP hired resident engineer for Bukit Kukus project’

GEORGE TOWN: The Penang Island City Council (MBPP) appointed a resident engineer and an independent checking engineer even before the start of the Bukit Kukus paired road project, says Chief Minister Chow Kon Yeow.

“If you see the action taken by MBPP, they understand their technical insufficiency in terms of a geotechnical engineer. That’s why in the contract, they required the main contractor to appoint a resident engineer, who was paid by MBPP to monitor the project on MBPP’s behalf.

“The independent checking engineers were also paid by MBPP. So, it was a measure taken by MBPP even before the start of the project, knowing that this is a big project.

“They did not have the capacity to monitor the project as they have only two or three engineers who have to be looking at other matters besides this project.

“So, they took action to appoint a resident engineer as well as independent checking enginners to act on behalf of MBPP,” he told reporters at the Penang Development Corp­oration Chinese New Year celebration at the PDC office in Bayan Lepas yesterday.

Chow also said the state would wait for the Department of Occupational Safety and Health (DOSH) report first.

“We will leave it to DOSH’s findings. Let DOSH come out with the report and we will take the necessary action after that,” he said.

Asked if MBPP had to bear necessary compensation for families of the victims of the landslide last October, Chow said MBPP had not received any claim so far.

Chow was asked to respond to the Con­sumers Association of Penang’s (CAP) call for stern action to be taken against the wrongdoers responsible for the tragedy.

CAP president S.M. Mohamed Idris in a statement yesterday said: “While we welcome the investigation committee’s findings as to who is responsible for the tragedy, we are concerned that apart from recommending the blacklisting of the contractor, consultant and independent checking engineer from any tender consideration for future projects, it appears that no further stern action has been recommended.

“In particular, we want to know what action will be taken against MBPP,” he said.

Deputy Chief Minister I Datuk Ahmad Zaki­yuddin Abdul Rahman, who headed the investigation panel, was reported yesterday as saying that MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired road project had not adhered to construction and engineering best practices.

Meanwhile, MBPP acknowledged responsibility for the Bukit Kukus landslide tragedy as it is the council’s project.

MBPP mayor Datuk Yew Tung Seang said the council was not pushing away any responsibility or negative comments on the council and project, and that it would be taken seriously. - By Cavina Lim and Intan Amalina Mohd Ali, The Star

Penang landslide report blames contractor, MBPP and DOSH

The special investigative panel report on the Bukit Kukus landslide had not been made public, but excerpts of the findings were made available by the state.

However, it has raised more questions than answers as the state blamed the contractor, Penang Island City Council (MBPP) and the Department of Occupational Safety and Health (DOSH).

In an immediate response, DOSH Penang director Jaafar Leman denied the department was to be blamed for the landslide.

“We were not even invited to be part of the investigative panel to give our views. How could we be blamed?” he asked.

According to the statement by Deputy Chief Minister 1 Datuk Ahmad Zakiyuddin Abdul Rahman who headed the investigative panel, the stop-work order on Oct 17 prevented contractors from entering the site to do maintenance works.

As a result, the temporary toe drain overflowed and water was retained on the reclaimed land contributing to the collapse of the slopes.

“How could a stop order which was issued on Oct 17 contribute to the landslide which occurred on Oct 19?” asked Jaafar.

He said the slopes would have been risky from the beginning as the contractor did not do any mitigation works to strengthen them and it does not make sense to blame DOSH.

The stop-work order was issued on Oct 17 after 14 beams fell in a ravine.

Earlier, during a press conference, Ahmad Zakiyuddin said MBPP and other parties involved in the construction of the Jalan Bukit Kukus paired roads project, had not adhered to construction and engineering best practices.

“The landslide was caused by many factors, which included a temporary construction of a platform to place machinery which was not constructed properly. The temporary platform was created to allow heavy vehicles lift beams for the paired road project.

“MBPP, as owners of the project, had failed to ensure all the hired parties carried out their job.

“MBPP had failed to hire a professional engineer for temporary works to design and supervise the site,” he said yesterday.

Ahmad Zakiyuddin said another factor was the downpour in the morning of the day of the landslide.- The Star


Related news


Contractor fined for negligence in Bukit Kukus landslide

 


Cash flow issues slowing Bukit Kukus road progress, says Penang ...


Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide tragedy. The inquiry still begs a lot of questions, e.g. why was the contract given to Yuta Maju from Terengganu? Could the accident have been prevented if a proper EIA was done? It is not just a "bureaucratic hurdle" but supposed to identify risks and advise mitigation. If the authorities wish to go on with the project, it is not too late to commissi...
See more

 “This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.

“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.
Metro News14 Jan 2019


Bukit Kukus road project illegal, says consumer group | Free Malaysia ..

 

Penang blacklists contractor, engineers in Bukit Kukus road project ...

 

Groups demand Penang govt release Bukit Kukus landslide probe ...

 

Bukit Kukus project to proceed with extra caution - Nation



Related:   



Back on track after snags - Metro News
Authorities inspecting the construction site of a section of the RM545.6mil Jalan Bukit Kukus paired road project. — Photos: CHAN BOON KAI/The Star


Action taken over irregularities at Bukit Kukus paired road project Penang

 

Soil erosion mitigation plans ignored, waters from stream identified as main cause !

 

Penang Landslide occured days after remedial works started

 

Penang landslides & flooding are natural disasters man-made?

 

 Call for action on flooding solution

 

Structural defects to blame, stop history repeating itself !

 

 Fake Awards Scam for Penang Island City Council, Seberang Perai Municipal Council !

 
Dubious honours: (Above) Former Penang Island City Council mayor Patahiyah Ismail with the trophy and certificate for Best Municipal Manager awards in 2013 while her Seberang Prai counterpart Maimunah (pictured here with the Chief Minister Lim Guan Eng and his aide Wong Hon Wai) received the same latter award in 2014

  Malaysian Public varsities, companies, GLC execs also recipients of EBA fake awards

 

Wednesday, February 13, 2019

Members of Economic Action Council (EAC)


The Prime Minister’s Office (PMO) announced the establishing of the Economic Action Council (EAC), which will respond to and take action to address economic issues faced by the public, based on their feedback.

“The main objectives of the council are to stimulate economic growth, ensure fair distribution of wealth and improve the well-being of the people. The council will also focus on issues related to costs of living, labour, poverty and home ownership,” it said in a statement today.

Members of the council include Prime Minister Tun Dr Mahathir Mohamad as chairman, along with Economic Affairs Minister Datuk Seri Azmin Ali, Finance Minister Lim Guan Eng, International Trade and Industry Minister Datuk Ignatius Darell Leiking and the Prime Minister’s economic adviser Dr Muhammed Abdul Khalid.

Other members of the council include former International Trade and Industry Minister Tan Sri Rafidah Aziz, Permodalan Nasional Bhd chairman Tan Sri Zeti Akhtar Aziz and Council of Eminent Persons member Prof Dr Jomo Kwame Sundaram.

A list of corporate leaders are also members of the EAC, such as Public Bank Bhd managing director Tan Sri Tay Ah Lek, Majlis Amanah Rakyat chairman Dr Hasnita Hashim and Bursa Malaysia chairman Datuk Shireen Ann Zaharah Muhiudeen.

Asean Business Advisory council chairman Tan Sri Dr Mohd Munir Abdul Majid, Federation of Malaysian Consumers Association (FOMCA) chief executive officer Datuk Dr Paul Selvaraj, lawyer Bah Tony @ Amani William Hunt Abdullah and MASA institute board of trustees member Nizam Mahshar are also in the EAC.  - The Edge

Council to drive economy forward

It will also look into issues related to cost of living, employment and home ownership

The Prime Minister and his key economic and finance ministers feature in a 16-strong committee that will form the Economic Action Council.

It will examine and decide on the economic and financial affairs and welfare of the people.

“The council was formed to respond and act on the feedback of the masses on the problems they face, particularly in the field of economy.

“The main aim of the council is to encourage and stimulate sustainable economic growth, equitable distribution of wealth and further enhance the well-being of the people.

“The council will also look into issues related to the cost of living, employment, poverty and home ownership,” said a statement from the Prime Minister’s Office yesterday. (See graphic for list of members)

The move is timely and a positive step in the right direction, said Socio-Economic Research Centre executive director Lee Heng Guie.

He said the council was expected to draw up immediate and medium-term priorities to sustain the country’s economic growth and development.

“Among these include the measures to address cost of living as well as to ease the cost of doing business and compliance costs.

“Structural policies and reforms have to be stepped up, in particular in skilled manpower, public sector delivery and efficiency, exports capacity, develop innovative and creative industries and the digital economy,” Lee told The Star.

Echoing a similar stance, AmBank Group chief economist Anthony Dass said the council was similar to the one formed in 1998 during the Asian Financial Crisis.

“However, this time around, the council will focus on ways to address economic headwinds and how to drive the domestic economy amid the challenges,” he said.

The old NEAC (National Economic Action Council) was formed to navigate Malaysia out from the worst recession in a generation.

Dass added that the formation of the Economic Action Council was timely, considering the current challenges that had affected the macroeconomic conditions and the rakyat.

“The council’s composition is broad and well-mixed, a variety of experience and expertise and the council will have to find measures to stimulate the economy, continue economic expansion and ensure that the machineries of the government can work with the private sector to drive the economy,” he said.

The council, he added, must identify areas that could be areas of growth and also add to public revenue.

“It must also focus on the new key areas such as the digital economy and how can the government encourage the adoption of digitalisation across industries, particularly among SMEs.

“The working group under the council is also important, to ensure the success of the execution,” he said.

The main brickbat the composition of the council has drawn is the absence of younger faces.

“It is the same ministers and academics and where are the business people and entrepreneurs?” asked a political analyst.

Another source who declined to be named said younger people would have brought different perspectives to the council and offered an independent voice in the formation of ideas and policies.

He said such voices would probably be sourced from the working groups the Economic Action Council would have featured at the high-level main committee. - by jagdev singh sidhuganeshwaran kana



Related:


Kadir: Ministers may not be good enough, hence the EAC - Nation ...



PM: Ministers not weak, but EAC a necessity



Azmin: EAC not due to Cabinet's poor performance - Nation

 

Quick results expected from EAC - Letters 

 



Wide-ranging issues for council to deal with - Nation


Experts urge council to excite people with proposals - Nation