Thursday, January 25, 2018

Penang Landslide occured days after remedial works started

Cracks at Tanjung Bungah site began in June, Commissioner of Inquiry told

Expert panel: (From right) Yeo, Dr Gue and Prof Ramli arriving for the inquiry.
 
GEORGE TOWN: A temporary structure supporting a worksite slope in Tanjung Bungah developed cracks in mid-June, a Commissioner of Inquiry heard.

Soil Mechanic Sdn Bhd director Cheah Wing How, who was a sub-contractor of the project where a landslide killed 11 workers, said he was informed by a clerk to carry out remedial works as the granite wall had cracked.

Cheah said his team left after completing the granite works and soil-nailing works to enhance the stability of the temporary slope.

There was, however, no mention when they completed the works.

“When we returned, we found there were pile cap excavation works carried out near the slope.

“We believe there was soil movement that resulted in the cracks on the granite wall.

“We were carrying out remedial works and 11 days into the job, the landslide happened,” said Cheah, who has 20 years’ experience in the field.

Cheah was testifying on the first day of the public hearing into the landslide tragedy by the State Commission of Inquiry (SCI) at City Hall in Esplanade yesterday.

On Oct 21, last year, a landslide hit the affordable condominium project made up of two 49-storey towers with 980 units in total within the Permai Village township near the Tunku Abdul Rahman University College.

Among the 11 killed was site supervisor Yuan Kuok Wern, 27.

During the proceeding, the Penang Island City Council (MBPP) also presented eight drone videos that showed the slope and the surrounding area after the tragic incident.

SCI chairman Datuk Yeo Yong Poh said they planned to carry out a site visit tomorrow.

He also fixed the hearing to continue until Monday, followed by Feb 8 to Feb 11, March 24 to March 28 and April 18 to 25.

Other members of the commission are geotechnical expert Datuk Dr Gue See Sew and forensic geo-technical engineer from Universiti Teknologi Malaysia Prof Ramli Nazir.

The SCI was gazetted on Dec 21 last year to investigate the landslide after Yang di-Pertua Negri Tun Rahman Abbas gave his consent on Dec 6, 2017, for the appointment of the members of the commission and its terms of reference.

Meanwhile, Penang Citizens Awareness Chant Group (Chant) adviser Yan Lee said the entrance to the Teik Granite Quarry, which is located near the site where the landslide occurred, should be fenced up.

“Anyone can just walk into the site as the safety measure is not up to mark.

“We have voiced our concern to the Penang Island City Council, the Department of Environment as well as the Land and Mines Department,” he said yesterday.

By Chong Kah Yuan and Jo-Leen Wong The Star
 
Related Links:

Contractors in jitters over temporary slopes - Nation

 

Boulders slid down hill prior to disaster - Nation




Related posts:

Penang landslide tragedy, plea went unheeded, no one listened !

 

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'..

Penang Landslide occured days after remedial works started

Cracks at Tanjung Bungah site began in June, Commissioner of Inquiry told


Expert panel: (From right) Yeo, Dr Gue and Prof Ramli arriving for the inquiry.
 
GEORGE TOWN: A temporary structure supporting a worksite slope in Tanjung Bungah developed cracks in mid-June, a Commissioner of Inquiry heard.

Soil Mechanic Sdn Bhd director Cheah Wing How, who was a sub-contractor of the project where a landslide killed 11 workers, said he was informed by a clerk to carry out remedial works as the granite wall had cracked.

Cheah said his team left after completing the granite works and soil-nailing works to enhance the stability of the temporary slope.

There was, however, no mention when they completed the works.

“When we returned, we found there were pile cap excavation works carried out near the slope.

“We believe there was soil movement that resulted in the cracks on the granite wall.

“We were carrying out remedial works and 11 days into the job, the landslide happened,” said Cheah, who has 20 years’ experience in the field.

Cheah was testifying on the first day of the public hearing into the landslide tragedy by the State Commission of Inquiry (SCI) at City Hall in Esplanade yesterday.

On Oct 21, last year, a landslide hit the affordable condominium project made up of two 49-storey towers with 980 units in total within the Permai Village township near the Tunku Abdul Rahman University College.

Among the 11 killed was site supervisor Yuan Kuok Wern, 27.

During the proceeding, the Penang Island City Council (MBPP) also presented eight drone videos that showed the slope and the surrounding area after the tragic incident.

SCI chairman Datuk Yeo Yong Poh said they planned to carry out a site visit tomorrow.

He also fixed the hearing to continue until Monday, followed by Feb 8 to Feb 11, March 24 to March 28 and April 18 to 25.

Other members of the commission are geotechnical expert Datuk Dr Gue See Sew and forensic geo-technical engineer from Universiti Teknologi Malaysia Prof Ramli Nazir.

The SCI was gazetted on Dec 21 last year to investigate the landslide after Yang di-Pertua Negri Tun Rahman Abbas gave his consent on Dec 6, 2017, for the appointment of the members of the commission and its terms of reference.

Meanwhile, Penang Citizens Awareness Chant Group (Chant) adviser Yan Lee said the entrance to the Teik Granite Quarry, which is located near the site where the landslide occurred, should be fenced up.

“Anyone can just walk into the site as the safety measure is not up to mark.

“We have voiced our concern to the Penang Island City Council, the Department of Environment as well as the Land and Mines Department,” he said yesterday.

By Chong Kah Yuan and Jo-Leen Wong The Star

Related Links:

Contractors in jitters over temporary slopes - Nation

 

Boulders slid down hill prior to disaster - Nation





Related posts:

Penang landslide tragedy, plea went unheeded, no one listened !

 

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.  Approximate Coordinates : 5°20'38.47"N,100°16'..

Tuesday, July 25, 2017

The stalled building defects causing delays of relocation ..

Not ready: (Clockwise from top) The front view of the Batu Ferringhi market in Penang, exposed electrical sockets and cracked floor in the badminton court, and a leaking pipe in the washroom.


Defects causing delay of move to RM9mil Batu Ferringhi market


The scheduled relocation of traders to the RM9mil Batu Ferringhi market on Aug 14 is postponed to a later date until shortcomings such as leakage in the washrooms and cracks on the floor are fixed.

Lim checking on the condition of the market.- Photos: ZHAFARAN NASIB/The Star

SENIOR officers of the Penang Island City Council (MBPP) were left red-faced after Chief Minister Lim Guan Eng spotted several defects in the almost completed RM9mil Batu Ferringhi market during a site visit.

Lim, who was irked with the shortcomings, asked his officers to collect back copies of his text speech given earlier to reporters.

“Before I came in, I went to the washroom. I thought it would be ready.

“But the male washroom was locked and I had to use the unoccupied ladies washroom instead.

“If the market is considered ready (by the council), then it is unacceptable,” he said.

Washroom with missing taps

 
A leaking pipe pipe in the washroom

It is learnt that the ladies washroom was leaking and some of the taps had yet to be fixed.

Lim, who was walking to the dining area, was stopped by several traders who requested the council delay their relocation into the market which was earlier scheduled on Aug 14.

Speaking to newsmen, Lim said another date would be set.

“We cannot fix a date now until we are satisfied that the shortcomings have been rectified,” he said.

MBPP mayor Datuk Maimunah Mohd Sharif said she would hold discussions with the market contractor and architect.

“Cracks have also appeared on the floor of the badminton courts,” she said.


Maimunah said the council had issued the Certificate of Practical Completion (CPC) for the market but not the Certificate of Completion and Compliance (CCC).

The market was scheduled for completion by the end of last year.

There are 16 hawker stalls, 28 wet and dry market units, a multipurpose hall, a library, three badminton courts, playground, bicycle path, shower rooms and 90 parking bays.

Source: The Star/ANN by Intan Amalina Mohd Ali

Related Link:

Residents: Removed plants were well maintained - Community 

Related posts:

Wall and awning collapsed in house near construction site 

 

Errant hill clearing by developers causes of flood, sinkholes, seepages damaged houses!

The stalled building defects causing delays of relocation ..

Not ready: (Clockwise from top) The front view of the Batu Ferringhi market in Penang, exposed electrical sockets and cracked floor in the badminton court, and a leaking pipe in the washroom.


Defects causing delay of move to RM9mil Batu Ferringhi market


The scheduled relocation of traders to the RM9mil Batu Ferringhi market on Aug 14 is postponed to a later date until shortcomings such as leakage in the washrooms and cracks on the floor are fixed.

Lim checking on the condition of the market.- Photos: ZHAFARAN NASIB/The Star

SENIOR officers of the Penang Island City Council (MBPP) were left red-faced after Chief Minister Lim Guan Eng spotted several defects in the almost completed RM9mil Batu Ferringhi market during a site visit.

Lim, who was irked with the shortcomings, asked his officers to collect back copies of his text speech given earlier to reporters.

“Before I came in, I went to the washroom. I thought it would be ready.

“But the male washroom was locked and I had to use the unoccupied ladies washroom instead.

“If the market is considered ready (by the council), then it is unacceptable,” he said.

Washroom with missing taps

 
A leaking pipe pipe in the washroom

It is learnt that the ladies washroom was leaking and some of the taps had yet to be fixed.

Lim, who was walking to the dining area, was stopped by several traders who requested the council delay their relocation into the market which was earlier scheduled on Aug 14.

Speaking to newsmen, Lim said another date would be set.

“We cannot fix a date now until we are satisfied that the shortcomings have been rectified,” he said.

MBPP mayor Datuk Maimunah Mohd Sharif said she would hold discussions with the market contractor and architect.

“Cracks have also appeared on the floor of the badminton courts,” she said.


Maimunah said the council had issued the Certificate of Practical Completion (CPC) for the market but not the Certificate of Completion and Compliance (CCC).

The market was scheduled for completion by the end of last year.

There are 16 hawker stalls, 28 wet and dry market units, a multipurpose hall, a library, three badminton courts, playground, bicycle path, shower rooms and 90 parking bays.

Source: The Star/ANN by Intan Amalina Mohd Ali

Related Link:

Residents: Removed plants were well maintained - Community 